RE:[sap-log-mm] Replacement Materials and MRP

Reply from sop57 on Mar 14 at 10:54 AM
On the MRP4 screen of the material master there is a section called "Discontinued Parts" in which you can enter the follow-up material and set how it will work.

---------------Original Message---------------
From: Michael Pontau
Sent: Tuesday, March 13, 2012 2:55 PM
Subject: Replacement Materials and MRP

How do I keep MRP from ordering an obsolete part?

Reply to this email to post your response.