Reply from ha_tran on Feb 7 at 6:48 PM
Hi,

Since MRP run will generate scheduling agreement delivery schedule line directly, your existing PR release strategy won't be available. Therefore, you should revisit your approval process and decide if the SA with release documentation shall be used instead of normal scheduling agreement.

Cheers,
HT

---------------Original Message---------------
From: ian inkson
Sent: Tuesday, February 07, 2012 5:26 AM
Subject: From Purchase Reqs and Orders to Schedule Agreements and Lines

Hi All

My client currently use's MRP to create purch reqs which are released via ME58. Then they create purchase order's via ME21N.
They want to go to schedule agreements with vendors, so MRP will create a schedule line automatically and this can then be faxed to the vendor.
Is there any config change needed going from purchase reqs and orders to schedule agreements and lines

Regards,

Ian

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran  
Senior SAP Supply Chain Business Analyst
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 Response to "RE:[sap-log-mm] From Purchase Reqs and Orders to Schedule Agreements and Lines"

Post a Comment