RE:[sap-log-mm] PR From MRP Run, Planned Orders

Posted by ha_tran (Senior SAP Supply Chain Business Analyst)
on Sep 15 at 6:26 PM
Hi,

The source of supply will only be assigned to the proposed procurement element (planned order or purchase requisition) on the condition that the source list record is maintained with MRP-relevant indicator being set as "1".

Cheers,
HT

---------------Original Message---------------
From: vibhuti lal
Sent: Thursday, September 15, 2011 8:16 AM
Subject: PR From MRP Run, Planned Orders

Hi All,

I have two plants and during MRP RUN for both the plants,for plant 'A' the Purchase requisition is getting generated from planned orders during which info records can been seen automatically. Where as for plant 'B' Purchase Requisition is getting generated from MRP DIRECTLY. No info records can be seen for seeing the info records. I have to manually do it.

Can anybody suggest what can be the possible solution for getting the info records automatically when PR is getting created from MRP.

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
ha_tran
SAP Logistics Material Management Top Contributor

Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement
Popular White Papers

In the Spotlight
View the "Managing the Application Life Cycle" webinar and learn how organizations optimize their SAP applications.

_.____.__

0 Response to "RE:[sap-log-mm] PR From MRP Run, Planned Orders"

Post a Comment