RE:[sap-log-mm] MRP rescheduling dates and planning calendars / cycles

Posted by stuart lowe (Supply Chain)
on May 10 at 7:33 PM
You need to change your lot size PK in configuration. Transaction OMI4, change the scheduling indicator from blank to your requirement.

Best regards

Stuart

---------------Original Message---------------
From: MarkMahoney
Sent: Tuesday, May 10, 2011 6:14 AM
Subject: MRP rescheduling dates and planning calendars / cycles

MRP will calculate a rescheduling date on a purchase order or fixed purchase req depending on the requirements.

However the date calculated does not take into account the planning calendar / planning cycle that has been allocated to the material in material master.

For example,
A material could have a planning calendar set to it, to allow the delivery date on the PO to fall on Tuesdays.

MRP could calculate the 'rescheduling in' date to be 25.05.2011 (Wednesday) yet if the planning calendar was taken into account it should read 24.05.2011 (Tuesday).

Is there a SAP solution to allow MRP to take planning calendars into account when calculating the reschedule date.

Thanking in advance,
Mark Mahoney

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
stuart lowe
SAP Logistics Material Management Helper

Posted helpful replies on 5 threads in a group to earn a Bronze Achievement
Popular White Papers

In the Spotlight
Which response to your Toolbox.com Groups post was the most helpful? Use 'Best Answer' to mark highest quality content.
_.____.__

0 Response to "RE:[sap-log-mm] MRP rescheduling dates and planning calendars / cycles"

Post a Comment