RE:[sap-log-mm] Still Able to Un-release PO after GR

Reply from ha_tran on Feb 28 at 7:21 PM
Hi,

It is of SAP standard functionality that the release strategy activation is not subject to the availability of any follow-on document. The justification is that it will allow end users full flexibility of getting your PO updated to cater for unplanned requirements after either GR or IR were created.

Cheers,
HT

---------------Original Message---------------
From: Heryanto .
Sent: Monday, February 27, 2012 11:08 AM
Subject: Still Able to Un-release PO after GR

I've released a Purchase order and made a GR for that, why I still can un-release PO without cancel GR first? How to avoid this? Is this a standard SAP ?

Thx.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran  
Senior SAP Supply Chain Business Analyst
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 Response to "RE:[sap-log-mm] Still Able to Un-release PO after GR"

Post a Comment