RE:[sap-log-mm] Replacement Materials and MRP

Reply from Vaishali gupta on Mar 14 at 7:43 AM
Hi Michael,

There are different way to exclude the mateial from MRP.

1)Active deletion falg,

2)MRP Type ND,

3)MRP 4 vie don't plan dependent requirement from header material,

4) X-material status.

Also, you can exclude material from MRP run by selecting Procurement Type as No Procurement in MRP-2 View in Material Master.


Also you can select X-plant / Plant specific Material status as :


01 Blocked for procment/whse to block materila from MRP run.

---------------Original Message---------------
From: Michael Pontau
Sent: Tuesday, March 13, 2012 2:55 PM
Subject: Replacement Materials and MRP

How do I keep MRP from ordering an obsolete part?

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Vaishali gupta  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 Response to "RE:[sap-log-mm] Replacement Materials and MRP"

Post a Comment