Question from ianinkson on Feb 7 at 5:25 AM
Hi All

My client currently use's MRP to create purch reqs which are released via ME58. Then they create purchase order's via ME21N.
They want to go to schedule agreements with vendors, so MRP will create a schedule line automatically and this can then be faxed to the vendor.
Is there any config change needed going from purchase reqs and orders to schedule agreements and lines

Regards,

Ian
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ianinkson  
 
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 Response to "[sap-log-mm] From Purchase Reqs and Orders to Schedule Agreements and Lines"

Post a Comment