RE:[sap-log-mm] Early Goods Receipt against Schedule Line

Reply from ha_tran on Feb 12 at 8:26 PM
Hi SOP57,

The requirement is not about over or under-delivery tolerance setting but early goods receipt posting. Did you manage to achieve it using SA?


---------------Original Message---------------
From: TFEwines
Sent: Thursday, February 09, 2012 2:08 PM
Subject: Early Goods Receipt against Schedule Line

Hello All;

We would like the system to allow a GR against a Schedule Line earlier than the scheduled delivery date, without having to maintain the date in ME38. I have read through the related posts and have not found a definitive answer as to how to do this.

I have modified my settings in MIGO to Propose All Items, which does allow MIGO to display the schedule line. But when I try to do the GR, I receive the message "PU Ordered quantity exceeded by 13.000 EA : 10049002 SH10 1800". This is a legitimate hard error for PO's we want to keep in place, but is being displayed in the case of the early receipt as well. The scheduling agreement I am trying to do an early receipt on has sufficient open quantity, so system must be looking again for a schedule line dated today.

Does anyone know if ECC6.0 has any settings to allow an early GR on a schedule line?

Thanks in advance, Terry

Reply to this email to post your response.
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
Copyright © 2012 and message author. 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Senior SAP Supply Chain Business Analyst
Mark as helpful
View this online
Ask a new question
In the Spotlight
Become a blogger at and share your expertise with the community. Start today.


0 Response to "RE:[sap-log-mm] Early Goods Receipt against Schedule Line"

Post a Comment