Re: [sap-log-mm] Price of Material in Subcontracting PO

Reply from ravindra-joshi on Feb 2 at 8:33 AM
First maintain subcontracting purchase info record and in the condition
tab maintain your price. The price is coming from info record to purchase order.

---------------Original Message---------------
From: dashingguy5452
Sent: Thursday, February 02, 2012 8:05 AM
Subject: Price of Material in Subcontracting PO

While creating a subcontracting PO, I am first entering all the details but not the plant. So, the price of the material is taken as 1100 as it is in the info records. But as soon as I enter the plant and hit enter, the price changes to 1000. Why is this happening?

Is it taking the price of material from the material master and not the info records? What if I want the price to be 1100 only and I don't want to do it manually?

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ravindra-joshi  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 Response to "Re: [sap-log-mm] Price of Material in Subcontracting PO"

Post a Comment