Reply from mikepmoss on Feb 8 at 10:25 PM
Hi,

As far as I know, no problems in that way of working. It is actually the way we have worked.

Regards,

Mike

Michael Moss CITP LLB MBCS

---------------Original Message---------------
From: VFRMark
Sent: Wednesday, February 08, 2012 3:39 PM
Subject: From Purchase Reqs and Orders to Schedule Agreements and Lines

Hi Mike,

We leave MRP defaulted to 3 even if not set up for schedules and since we are not planning over a long time I have no issues with 2 or 3 but since 80% of orders are not schdules but we run with 3 as the default do you see any issues (non spotted so far)
thanks

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
mikepmoss  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 Response to "RE: [sap-log-mm] From Purchase Reqs and Orders to Schedule Agreements and Lines"

Post a Comment