RE:[sap-log-mm] Vendor+Article Specific Delivery Calendar

Reply from sop57 on Jan 1 at 6:26 PM
Hi,
You can set up a planning calendar via MD25 to contain the required delivery dates, then in the material master enter the planning calendar you have thus created. You will need to config a new lot size type, because although SAP has the planning calendar functionality, there is not a standard lot size key which activates this functionality. You can use the same planning calendar for as many materials as required, but I do not think you can make it vendor specific if you have more than one source of supply specified for a material.
Regards,
SOP57

---------------Original Message---------------
From: Kit-Kwan
Sent: Friday, December 30, 2011 10:50 AM
Subject: Vendor+Article Specific Delivery Calendar

Hi, I would like to maintain a vendor+article specific calendar such that during the re-order planning, the planned delivery date would fill in dates of this calendar, would anyone tell me how to achieve this, Thanks

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
sop57  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 Response to "RE:[sap-log-mm] Vendor+Article Specific Delivery Calendar"

Post a Comment