In detail of Release code you have following options in Changeability Field.

Blank Changeable, new release in case of new strategy
1 Cannot be changed
2 Changeable, no new determination of strategy
3 Changeable, new release in case of new strategy
4 Changeable, new release in case of new strat. or val. change

---------------Original Message---------------
From: Serdar Derinel
Sent: Wednesday, January 25, 2012 4:51 AM
Subject: Changes in Purchase Requisition after Release?

Hi there,

Is there any way in SAP customizing to make any field change in a Purchase requisition or is it impossible after the Purch Req. has been released by any of the release codes? We use Purch.Req. release procedure by classification.

The purchase requisitions are created manually by persons (not by MRP run). We constructed the release procedure so that when a change in the price or in any field happens, the release procedure all-over starts from the beginning release code. But we do not want the release procedure start again due to changes in the Purch Req.

Regards,
Serdar

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ZainabKaleem  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 Response to "RE:[sap-log-mm] Changes in Purchase Requisition after Release?"

Post a Comment