For a material that is being inventorised, the demand is available for multiple WBS. MRP provides Purchase Requisition for each WBS separately. Unable to achieve material code wise cumulation in PR Item level. In PO also this cumulation can not be carried out. So for the same matterial, multiple line items are printed, for which vendors are objecting as it increases their documentation charges. Account assignments are insignificant for the vendors. Its only the material code and Quantity.


---------------Original Message---------------
From: mohan KARUPPIAH
Sent: Thursday, December 08, 2011 11:43 AM
Subject: Multiple Account Assignment in Purchase Requisition

We want to combine the requirements of Multiple Account Assignment in a Single Purchase Requisition Line Item for a material code identified as "Individual(Q)" in material master. We are in 4.7 Version. System does not allow. We are planning to upgrade to ECC 6.0 EHP 5. Is this provision available in the new version? Please confirm.


Copyright © 2011 and message author. 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
Popular White Papers

In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements


0 Response to "RE:[sap-log-mm] Multiple Account Assignment in Purchase Requisition"

Post a Comment