RE:[sap-log-mm] Release Key Function in SAP Engineering Change Orders

Posted by stuart lowe (Supply Chain)
on Nov 8 at 6:17 PM
You can use the change master status, change master effective date or use the discontinued parts method on the MRP4 view of the material master.

---------------Original Message---------------
From: Tom McLaughlin
Sent: Tuesday, November 08, 2011 10:16 AM
Subject: Release Key Function in SAP Engineering Change Orders

My company has multiple change orders for the same BOM and they need to control the release of specific components that are changed so they can maximize the use of old inventory.

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
stuart lowe
SAP Logistics Material Management Helper

Posted helpful replies on 5 threads in a group to earn a Bronze Achievement
Popular White Papers

In the Spotlight
SAP BusinessObjects: Dashboards and Analytics. Learn more about this Toobox.com Marketplace online course.

_.____.__

0 Response to "RE:[sap-log-mm] Release Key Function in SAP Engineering Change Orders"

Post a Comment