Hi H T,

Many thanks for your explanation & great support. I have made the changes as you suggested and getting standard message 06 042 now.

Regards
Suri..

---------------Original Message---------------
From: Suri H R
Sent: Tuesday, November 22, 2011 9:20 PM
Subject: Issue with Outline Agreement - Value Contract in SAP MM

Dear All,

I have created a value contract at company code level with target value as 10,000 INR. When I compute the overall cost of the material that I have entered in different items, it exceeds more than the target value (>10,000 INR) defined. However system is still allowing me to create contract without any warning or error message. I even created a purchase order with reference to contract whose overall cost exceeds the target value defined in contract without any warning or error message.

I'm suspecting I went wrong somewhere. Can someone advise where exactly I went wrong? Can we have a contract whose overall cost exceeds the target value defined?

Thanks in advance for your great support.

Regards
Suresh

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
SAP BusinessObjects: Dashboards and Analytics. Learn more about this Toobox.com Marketplace online course.

_.____.__

0 Response to "RE:[sap-log-mm] Issue with Outline Agreement - Value Contract in SAP MM"

Post a Comment