Hi Kaushai, Unfortunately, your understanding is incorrect as the project stock concept is different than what you have described (i.e. using the storage location as subcontractor). Shashank, Since SAP does not allow you to move any special stock (project stock, for instance) to subcontractor stock with standard movement type 541, you have to firstly move your special stock into unrestricted use stock and then move it to subcontractor stock with movement type 541. Cheers, HT
| | | ---------------Original Message--------------- From: Sandeepvijay Sent: Tuesday, June 19, 2007 7:15 AM Subject: Good issue to sub-contractor in 541 for a item having Q(project stock) a/c assignment category Hello, I am working on sub-contracting process through PS. I am trying to issue goods (free issue) to sub-contractor by movement 541 to make and provide us a final product (header item). I have selected item category L(sub-cotracting)for header item(final product) to create a PR & PO. I have selected A/c assignment category Q for issuing goods. But still I am not able to issue goods to sub-contractor. Pl. tell me solution whether is it possible to goods issue to sub-contractor with movement type 541 & A/c category Q. regards | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | ha_tran SAP Logistics Material Management Top Contributor
Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement Popular White Papers In the Spotlight SAP BusinessObjects: Dashboards and Analytics. Learn more about this Toobox.com Marketplace online course. _.____.__ |
0 Response to "RE:[sap-log-mm] Good issue to sub-contractor in 541 for a item having Q(project stock) a/c assignment category"
Post a Comment