RE:[sap-log-mm] Good issue to sub-contractor in 541 for a item having Q(project stock) a/c assignment category

Posted by ha_tran (Senior SAP Supply Chain Business Analyst)
on Nov 29 at 2:10 AM
Hi Kaushai,

Unfortunately, your understanding is incorrect as the project stock concept is different than what you have described (i.e. using the storage location as subcontractor).

Shashank,

Since SAP does not allow you to move any special stock (project stock, for instance) to subcontractor stock with standard movement type 541, you have to firstly move your special stock into unrestricted use stock and then move it to subcontractor stock with movement type 541.

Cheers,
HT

---------------Original Message---------------
From: Sandeepvijay
Sent: Tuesday, June 19, 2007 7:15 AM
Subject: Good issue to sub-contractor in 541 for a item having Q(project stock) a/c assignment category

Hello,

I am working on sub-contracting process through PS. I am trying
to issue goods (free issue) to sub-contractor by movement 541 to
make and provide us a final product (header item). I have
selected item category L(sub-cotracting)for header item(final
product) to create a PR & PO. I have selected A/c assignment
category Q for issuing goods.

But still I am not able to issue goods to sub-contractor.

Pl. tell me solution whether is it possible to goods issue to
sub-contractor with movement type 541 & A/c category Q.

regards

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
ha_tran
SAP Logistics Material Management Top Contributor

Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement
Popular White Papers

In the Spotlight
SAP BusinessObjects: Dashboards and Analytics. Learn more about this Toobox.com Marketplace online course.

_.____.__

0 Response to "RE:[sap-log-mm] Good issue to sub-contractor in 541 for a item having Q(project stock) a/c assignment category"

Post a Comment