RE:[sap-log-mm] Make the Unplanned Freight Posted to Material Cost

Posted by ha_tran (Senior SAP Supply Chain Business Analyst)
on Sep 23 at 11:25 PM
Hi,

Unfortunately, you have complicated unnecessarily your process simply to accommodate unplanned freight costs as far as I am concerned. It even results in more works / steps for your end users to do rather than making additional unplanned freight invoice posting via LIV process.

Cheers,
HT

---------------Original Message---------------
From: jack Lee
Sent: Wednesday, September 21, 2011 11:19 PM
Subject: Make the Unplanned Freight Posted to Material Cost

Dear experts,

We have a requirement that we order PO using move average price, Usually the material is transported by our material vendor in partial delivery and the freight cost is included in the price, but sometimes for the urgent purposes, we may inform a third party to handle the partial delivery.That means we don't know how many of the total quantities will be transported by the third party when PO is created. If I expect a cost using a freight condition in PO to treat this as a planned delivery cost, there must be some quantities of the GR/IR Freight not be cleared.

Does anybody experience a similar scenario,please give me an optimum solution .Thanks!

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
ha_tran
SAP Logistics Material Management Top Contributor

Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement
Popular White Papers

In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 Response to "RE:[sap-log-mm] Make the Unplanned Freight Posted to Material Cost"

Post a Comment