RE: [sap-log-mm] Error creating a PO: Not possible to determine shipping data for material XXXXXXX

Posted by satishvp123
on Sep 21 at 11:07 AM
1. In OMGN assign customer master number to receiving plant.
2. Assign sales org to supplying plant.
3. Master data for the customer master assigned to receiving plant must be created under sales org assigned to supplying plant, and shipping condition must be maintained in the sales data.
4. In Shipping config under LE, shipping point determination must be maintained for the above data.

Regards.

Satish.

---------------Original Message---------------
From: Andree Kurnaiwan
Sent: Wednesday, September 21, 2011 9:08 AM
Subject: Error creating a PO: Not possible to determine shipping data for material XXXXXXX

Try T Code OMGN. You should assign a customer master in a plant.


Andree

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  

_.____.__

0 Response to "RE: [sap-log-mm] Error creating a PO: Not possible to determine shipping data for material XXXXXXX"