Hi,
If you want to change the production confirmation then use co14 and if you
are confirming partially then go to co15 and change 261 movement qty.

Regards,

BC Malkani

---------------Original Message---------------
From: JAVED NASEER
Sent: Friday, September 23, 2011 3:56 PM
Subject: Consumption Quantity Change

Use co15 fro confirmation.