I have an overseas supplier that I would like to time phase deliveries against a PO.
So, I'd like to issue a PO for 5000 units but I would like them to deliver 1000 units per
month over 5 months. Can I do this in SAP?

---------------Original Message---------------
From: Karl Obo
Sent: Friday, August 19, 2011 10:58 AM
Subject: SAP Time-phased planning

Hello,

I am trying to use time-phased planning in MRP to create purchase requisitions for a supplier on a particular day of the week for delivery on the same day of the following week. To do this, I have made the following amendments in MM02:

MRP1 tab:
MRP Type - R3
Planning cycle - TUE

MRP2 tab:
Planning calendar - TUE

The Planning Calendar, TUE, uses weekly periods running from Tuesday to Monday.

After running MRP, purchase requisitions are correctly created during the initial calendar period.

The problem is that neither purchase requisitions nor planned orders are created after this, causing issues with providing forecasts to the supplier. I have tried modifying the MRP Type in Customizing and the periods for the planning calendar but without success.

We do not use forecasting for purchased items, relying solely on production requirements via MRP.

Do any of you have experience of using time-phased planning and is there any way of creating receipts after the initial period?

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
_.____.__

0 Response to "RE:[sap-log-mm] SAP Time-phased planning"

Post a Comment