RE:[sap-log-mm] Indicate Contract (outline agreement) in quota arrangement

Posted by Joregu (MM)
on Aug 4 at 3:52 AM
Thanks for your answer Ha Tran.

If the QA has priority over source lis/contract, is there a way to indicate the contract number in the QA?

---------------Original Message---------------
From: Ha Tran
Sent: Wednesday, August 03, 2011 6:35 PM
Subject: Indicate Contract (outline agreement) in quota arrangement

Hi,

The reason was due the fact that during source of supply determination, SAP will take quota arrangement over source list and/or contract.

Cheers,
HT