RE:[sap-log-mm] How to correct VL09 done on wrong date

Posted by ha_tran (Senior SAP Supply Chain Business Analyst)
on Aug 6 at 9:32 PM
Hi Emma,

There are two alternative options you can consider -

1) Make the related JV adjustment for your related G/L account(s) if you wish not to make any further goods movement posting; or
2) Make a new goods issue on the wrong date (on which your original cancelled GI document was posted) and then reverse this new GI on the wrong day (on which your original GI was posted).

Cheers,
HT

---------------Original Message---------------
From: Emma_W
Sent: Thursday, August 04, 2011 8:56 AM
Subject: How to correct VL09 done on wrong date

Hi

I have reversed a post goods issue using VL09 but on the wrong transaction date (the next month)
How can I reverse the reverse on the wrong date and then re-do the reverse on the correct date?

I hope that make sense!
Many thanks

Emma

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
ha_tran
SAP Logistics Material Management Top Contributor

Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement
Popular White Papers

In the Spotlight
View the "Managing the Application Life Cycle" webinar and learn how organizations optimize their SAP applications.
_.____.__

0 Response to "RE:[sap-log-mm] How to correct VL09 done on wrong date"

Post a Comment