Posted by
Sap Land
Sunday, 24 July 2011
15:27
Hi, Question 1: No, it is not feasible. Question 2: You can use the time-phase planning. Cheers, HT
| | | ---------------Original Message--------------- From: Devanshu Bhatia Sent: Friday, July 22, 2011 5:31 AM Subject: Is it possible to have multiple line items in single MRP PR ? Hi, I need guidance on the following points on urgent basis: 1. Is it possible to have multiple line items in single PR generated through MRP Run ? Is this possible by creating MRP Groups? 2. The next step thing I want is that PRs for MRP group A, B & C be created in 1st week of the month. D, E & F be created in the second week of the month etc. The scenario that I want to create is that the organization should have 'N' number of MRP controllers and each MRP Controller may have 'M' number of MRP Groups to handle. We also have long term rate contracts for materials. Please respond to the queries or provide references so that the issues may be addressed. Thanks ! | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | ha_tran SAP Logistics Material Management Top Contributor
Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement Popular White Papers In the Spotlight _.____.__ |
0 Response to "RE:[sap-log-mm] Is it possible to have multiple line items in single MRP PR ?"
Post a Comment