RE:[sap-log-mm] Restrict scope of planning, mrp, md01

Posted by ha_tran (Senior SAP Supply Chain Business Analyst)
on Jun 9 at 7:16 PM
Hi,

Through the configuration of your scope of planning, you can determine which plant(s) and/or MRP Area(s) shall be included. Is it something you are looking for?

Cheers,
HT

---------------Original Message---------------
From: 74VetGuy
Sent: Thursday, June 09, 2011 4:10 PM
Subject: Restrict scope of planning, mrp, md01

Is there a way to restrict "scope of planning" entries when using md01? We currently have a entry to allow for total corporate MRP run and we do not want anyone running this during the day.

We have the total corp MRP run set up in MDBT.

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
ha_tran
SAP Logistics Material Management Top Contributor

Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement
Popular White Papers

In the Spotlight
Visit IBM's Leveraging IT Services Briefing Center. Register now and learn how to deliver smarter security & resiliency.
_.____.__

0 Response to "RE:[sap-log-mm] Restrict scope of planning, mrp, md01"

Post a Comment