RE:[sap-log-mm] MRP type PD, safety time

Posted by edifi527
on Jun 16 at 6:08 AM
Aren't you describing Re-order point planning now?
We use Material Requirements Planning instead of ROP-planning.

---------------Original Message---------------
From: edifi527
Sent: Thursday, June 16, 2011 2:13 AM
Subject: MRP type PD, safety time

Hello everyone,

I have a question concerning MRP type PD (MRP). Does SAP consider delivery lead time when it releases a procurement proposal for material?

For example, lets say that you have a material with delivery lead time = 2 weeks and safety stock set to 0. You have released sales & planned orders for, say 9 weeks in the schedule with the first 3 weeks frozen, and SAP calculates that, with today's production plan, you will reach a zero stock level in 6 weeks. Does it release a procurement proposal TODAY or in week 4 (because the lead time is 2 weeks)? If the latter case is true, is there a way to set a safety time so that it releases a procurement proposal in, for example, week 3?

Best Regards,
Ed

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
Visit IBM's Leveraging IT Services Briefing Center. Register now and learn how to deliver smarter security & resiliency.
_.____.__

0 Response to "RE:[sap-log-mm] MRP type PD, safety time"

Post a Comment