Re: [sap-log-mm] Planning and posting production

Posted by sachin-jadhav
on Jun 23 at 12:56 AM
Hi,

You have done planning & production posting also. If you want to reverse all
these entries for new planning then do the following activities:

1.Reverse the Production posting with MF41-Document specific reversal or
with MFBF-Doc-Neutral reversal
2.Delete all created or open planned orders,production orders,purchase
req,purchase orders,schedule lines
3.Then delete the demand with MD74
4.Plan the activities again

If you have any doubt, Please contact.

Regards,
Sachin Jadhav
+91 9099052072

---------------Original Message---------------
From: blarebabe
Sent: Wednesday, June 22, 2011 9:26 AM
Subject: Planning and posting production

Hi,

I entered my planned production with md61,confirmed with mdbt, but I did not affirm with md04,
I posted production with mfbf but am having issues. Please how do O cancel all these steps have taken and do a new production planning?

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
Toolbox.com for iPhone & Android: Ask Questions & Get Answers Anywhere. Download the Free App
_.____.__

0 Response to "Re: [sap-log-mm] Planning and posting production"

Post a Comment