RE:[sap-log-mm] Clearing Reservations Not Used On a Plant Maintenance Work Order

Reply from ha_tran on Mar 3 at 9:47 PM
Hi,

Since the reservation is made directly from PM work order, the only solution to clear it is to adjust the quantity directly in the work order.

Cheers,
HT

---------------Original Message---------------
From: Rhonda Miller
Sent: Wednesday, February 29, 2012 2:10 PM
Subject: Clearing Reservations Not Used On a Plant Maintenance Work Order

how would you clear reservations on a plant maintenance order say your reserved 5 on the order but they only had 1 and 1 is all that was issued out and you didn't need the other 4?

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran  
Senior SAP Supply Chain Business Analyst
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Toolbox.com for iPhone & Android: Ask Questions & Get Answers Anywhere. Download the Free App

_.____.__

0 Response to "RE:[sap-log-mm] Clearing Reservations Not Used On a Plant Maintenance Work Order"

Post a Comment