Re: [sap-log-mm] Profit Center in Service Contract

Reply from sankar791 on Mar 14 at 3:12 AM
Hi,
Since you are creating service contract followed by service PO, if you are using
a/c assign category as K(cost centre) for expenses, the profit centre will
default from cost centre.

Sankar Naidu.

---------------Original Message---------------
From: Vamsi M
Sent: Tuesday, March 13, 2012 4:41 PM
Subject: Profit Center in Service Contract

Hi all,

When I create a service contract using a service material (Material type DIEN), the profit center from the service item is not carried over to the contract. The profit center is not automatiically getting derived from the material master. I did maintain the profit center in the Sales: General/Plant Data tab.

How do the get the Profit Center auto populated from service material master, as in the case of a regular sales order or material master.

Thanks,
Vamsi

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
sankar791  
Assistant Manager
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 Response to "Re: [sap-log-mm] Profit Center in Service Contract"

Post a Comment