RE:[sap-log-mm] Relation Between Source List and Material Master

Reply from ha_tran on Feb 21 at 6:24 PM
Hi Lynn,

There is not any linkage between the "source list" indicator checkbox in the material master and the "source determination" indicator checkbox in the PR. The fact is that by flagging the indicator checkbox in the material master, it allows SAP to validate and populate an error message if the source list record is not maintained for a particular combination of material and plant location when converting your PR into PO. The indicator in the PR, however, is used to allow an automatic source of supply determination.

Cheers,
HT

---------------Original Message---------------
From: Lynn Chua
Sent: Tuesday, February 21, 2012 3:44 AM
Subject: Relation Between Source List and Material Master

I've created a source list, info record for a material. I've also ticked the source list in the material master. When I create a PR, the info record for the material did not appear. What did I miss out?

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran  
Senior SAP Supply Chain Business Analyst
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 Response to "RE:[sap-log-mm] Relation Between Source List and Material Master"

Post a Comment