RE:[sap-log-mm] How to correct VL09 done on wrong date

Reply from Mostafa Ali on Feb 21 at 12:55 PM
Hi All,

@Ha Tran,

The system wouldn't accept to reverse on a date before the goods issue posting date.

Please advise

---------------Original Message---------------
From: Emma_W
Sent: Thursday, August 04, 2011 8:56 AM
Subject: How to correct VL09 done on wrong date

Hi

I have reversed a post goods issue using VL09 but on the wrong transaction date (the next month)
How can I reverse the reverse on the wrong date and then re-do the reverse on the correct date?

I hope that make sense!
Many thanks

Emma

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mostafa Ali  

achievement
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Toolbox.com for iPhone & Android: Ask Questions & Get Answers Anywhere. Download the Free App

_.____.__

0 Response to "RE:[sap-log-mm] How to correct VL09 done on wrong date"

Post a Comment