RE: [sap-log-mm] MRP type V2 with DepReq

Reply from sashkapoor on Feb 21 at 11:45 PM
Hi,

PD is good for firm requirement only .

You can set up reorder point manually in MRP type V1 and system generated by using V2.

What do you mean by "High Level Component" ?

Regards,

Sash Kapoor

---------------Original Message---------------
From: Tom King
Sent: Tuesday, February 21, 2012 10:54 AM
Subject: MRP type V2 with DepReq

Hi,

My goal is to get us ordering materials on time.

The MRP type we currently use is PD, which takes into account demand from higher level assemblies, this is desirable.
The negative is that is does not consider the reorder point to initiate a procurement proposal. The alternative is to use MRP type V2 which takes the reorder point in its calculation. However V2 does not consider demand from higher level components.
Is there some way of combining the two desirable behaviours? To use the reorder point and consider demand from components higher up in the BOM?

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
sashkapoor  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Toolbox.com for iPhone & Android: Ask Questions & Get Answers Anywhere. Download the Free App

_.____.__

0 Response to "RE: [sap-log-mm] MRP type V2 with DepReq"

Post a Comment