Reply from mikepmoss on Feb 7 at 10:49 AM
Hi,

Note that you should also modify the mrp parameter 'Delivery schedules' by setting it to 2 or 3.

Mike

---------------Original Message---------------
From: Philip Kreilein
Sent: Tuesday, February 07, 2012 5:36 AM
Subject: From Purchase Reqs and Orders to Schedule Agreements and Lines

Hi,

Not really. Create your schedule agreement(s) using ME31L.
Then create a source list record for the vendor/material Populate the schedule agreement number and line item number in the source list record.
Put a 2 in the MRP column.
This will cause MRP to create schedule releases against your schedule agreement.

Phil Kreilein
SAP TEAM LEAD SD and MM

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
mikepmoss  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 Response to "RE: [sap-log-mm] From Purchase Reqs and Orders to Schedule Agreements and Lines"

Post a Comment