Reply from ha_tran on Jan 9 at 7:04 PM Hi Mark, There are two options you can consider - 1) Create a separate storage location which is excluded from MRP run to stock your repairable items that are received through SO; or 2) Receive your repairable items and keep them in block stock status. Make sure that the related configuration to exclude block stock as part of current available stock shall be set. Cheers, HT
| | | ---------------Original Message--------------- From: MarkM Sent: Monday, January 09, 2012 12:20 PM Subject: MRP not to consider dependent requirements, but independent do. How can i set for not considering dependend requirements in MRP and just take independent requirments? I have a lot of sales and production orders that are affecting my MRP result and purchasing quantities | | Reply to this email to post your response. __.____._ | _.____.__ |