Question from abdul_baba on Dec 26 at 11:25 AM
Hi,

We have PR/PO was created initially with value of 300,000 and later PO was changed to 100,000. SES was issued with 100,000 and found that in remaining planning the balance amount (200,000) was held and we want to use it.
Your help is needed to sort out this issue.

Note: this PR created for one of operation in work order.

Thanks
Abdul.
 