Hi Chris,
Thanks for replying promptly.
the item changes only gives you the changes of the dates when the PO was created on and its only for one PO.
I am looking for the range of PO's and changes in their delivery dates.when you click on the confirmation tab in Item detail section of PO you see a Delivery date what if this date changes from the original delivery date.
I am looking for Report where I could see a list of PO's with their original and revised delivery dates.
Thanks
Celriz

---------------Original Message---------------
From: radkri Radha
Sent: Friday, December 02, 2011 11:13 AM
Subject: Transaction for viewing Expedite and De-expedite Report of Procure Material

Hi

I think you can view this in ME22N Select the line item and click the
environment and select Item changes, here you will find old and new values.
You can take report from Table CDHDR and CDPOS

Regards
Chris

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
Have you explored the Toolbox.com Marketplace? Learn more and access a free course now.

_.____.__

0 Response to "Re: [sap-log-mm] Transaction for viewing Expedite and De-expedite Report of Procure Material"

Post a Comment