Hi Asokh,

Please use Split Valuation for Separately for Air and Sea shipment.

Thanks & Regards,
Saravanan Kandasamy

---------------Original Message---------------
From: Jagadeesan Ashok
Sent: Tuesday, December 13, 2011 12:47 AM
Subject: How to Control the Moving Average Price in the SAP Material Master

Dear Experts,

Good Morning!

How to control the moving average price in the sap, because our material procuring methods in two separation one Sea shipment another one is air shipment

As you know Sea shipment transporting cost is lesser than the air lifted material, some times we do the ordering same materials in to sea or Air freight

Based on the urgency, but most of the material procured via sea transport, so moving price is defined is last procured price + transporting taxes etc…..

Is there any different moving price maintained in the material master for SEA and Air procured parts because our production cost + material cost is work based

On the moving price only, our costing shows the Particular Production order make loss because Moving average price is higher… even we procured the material via

Sea shipments. Why this happened know earlier we procured the same material via Air shipment….
With best regards,
J.Ashok

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
SAP BusinessObjects: Dashboards and Analytics. Learn more about this Toobox.com Marketplace online course.

_.____.__

0 Response to "RE: [sap-log-mm] How to Control the Moving Average Price in the SAP Material Master"

Post a Comment