RE:[sap-log-mm] In MIRO Distribute the Difference of Planned Delivery Costs

Posted by aalberawi
on Oct 31 at 3:59 AM
But I still can't really get it. The MIRO will not let us save unless the balance is zero and since the real amount is different than the one MIRO is assuming, there are a difference. What I need is to distribute this difference on the items.

---------------Original Message---------------
From: amer alberawi
Sent: Sunday, October 30, 2011 1:46 PM
Subject: In MIRO Distribute the Difference of Planned Delivery Costs

Dear All,

In MIRO and for the planned delivery costs of the PO, sometimes the real amount is different than what was set in the PO "it is known after the goods are received", and we try to set it in MIRO. When we put the right amount, a difference will occur in the balance field in the top of the screen.
Is there a way to distribute this difference on the lines of the PO" in the bottom of the screen" automatically. This is needed because some POs have a lot of lines, and distributing the differences manually will be a headache.
Thank you in advance.

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
Which response to your Toolbox.com Groups post was the most helpful? Use 'Best Answer' to mark highest quality content.

_.____.__

0 Response to "RE:[sap-log-mm] In MIRO Distribute the Difference of Planned Delivery Costs"

Post a Comment