RE:[sap-log-mm] Basic Unit Change

Posted by VFRMark (Logistics Improvement Manager (Global))
on Oct 13 at 8:16 PM
Hi Amar,
It is actually possible to change the base unit of measures but it is a pain. Basically SAP asks that you have 3 periods with no movements and that you have no "orders" (sales/po/production etc) outstanding. So its almost impossible in the practical world.

Far easier is to create a new part number, change BOMS and transfer all the stock to this.

You need to educate your teams, the base unit of measure must be the stocking UOM as you are able to have altenative UOM's for purchasing and selling.

Mark

---------------Original Message---------------
From: Amar Puhan
Sent: Sunday, October 09, 2011 2:20 PM
Subject: Basic Unit Change

Dear Sir,
I have maintain for some material Basic unit of measure as NOS in the material master and the issue of unit as KG.Now I want to change the basic unit of measure as M(Meter) for same item.Is this possible.If this how can I do this and what the T code will I use.

Regards
Amar Puhan

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 Response to "RE:[sap-log-mm] Basic Unit Change"

Post a Comment