RE: [sap-log-mm] PR From MRP Run, Planned Orders

Posted by satishvp123
on Sep 16 at 6:35 AM
Dear Vibhuti,

Maybe for the material you have multiple info records in Plant A, but only one info record in Plant B. Is this the case?

Regards.

Satish.

---------------Original Message---------------
From: vibhuti lal
Sent: Friday, September 16, 2011 5:11 AM
Subject: PR From MRP Run, Planned Orders

Hi HT,

Thanks for your reply,
for both materials we only have inforecords in the system. there is no source list/ quota arrangement/ contract/ scheduling agreements in the system.

Regards
V