[sap-log-mm] Is it possible to have multiple line items in single MRP PR ?

Posted by devanshubhatia
on Jul 22 at 5:30 AM
Hi,

I need guidance on the following points on urgent basis:
1. Is it possible to have multiple line items in single PR generated through MRP Run ? Is this possible by creating MRP Groups?

2. The next step thing I want is that PRs for MRP group A, B & C be created in 1st week of the month. D, E & F be created in the second week of the month etc.

The scenario that I want to create is that the organization should have 'N' number of MRP controllers and each MRP Controller may have 'M' number of MRP Groups to handle.

We also have long term rate contracts for materials.

Please respond to the queries or provide references so that the issues may be addressed.

Thanks !
__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
View this online
  
Popular White Papers

In the Spotlight
Toolbox.com for iPhone & Android: Ask Questions & Get Answers Anywhere. Download the Free App
_.____.__

0 Response to "[sap-log-mm] Is it possible to have multiple line items in single MRP PR ?"

Post a Comment