Posted by
Sap Land
Monday, 11 July 2011
04:46
Hi Ha Tran, Thanks for your response. I did not use hierarchical service specification in the contract line. Does this mean we can eliminate it as the cause of performance issue? Best Regards, Nicole
| | | ---------------Original Message--------------- From: nicoleng Sent: Thursday, July 07, 2011 5:31 AM Subject: PO created with reference to contract I have created a service PO with reference to a contract which has about 5 items and each item may have up to 6 service lines. All items and its service lines are adopted by the PO. The issue is when I click on the check button the process took 3 minutes. Is this normal because of the multiple items being adopted? | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |
0 Response to "RE:[sap-log-mm] PO created with reference to contract"
Post a Comment