RE:[sap-log-mm] PO created with reference to contract

Posted by ha_tran (Senior SAP Supply Chain Business Analyst)
on Jul 10 at 7:49 PM
Hi Nicole,

The use of service ID is as same as that for material ID where the service number is defined (via AC01/AC02/AC03 transaction) and assigned to your service line item in the contract. The hierarchical service specification enables you, on the other hand, to build your service specification in the structural level / manner. This is particularly useful when you are having the complicated project works.

Cheers,
HT

---------------Original Message---------------
From: nicoleng
Sent: Thursday, July 07, 2011 5:31 AM
Subject: PO created with reference to contract

I have created a service PO with reference to a contract which has about 5 items and each item may have up to 6 service lines. All items and its service lines are adopted by the PO. The issue is when I click on the check button the process took 3 minutes. Is this normal because of the multiple items being adopted?

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
ha_tran
SAP Logistics Material Management Top Contributor

Contributed the most posts in a group for 3 consecutive months to earn a Gold Achievement
Popular White Papers

In the Spotlight
Toolbox.com Marketplace: Take online training courses in SAP and other specialized areas of business and IT.
_.____.__

0 Response to "RE:[sap-log-mm] PO created with reference to contract"

Post a Comment