Hi THe overdelivery works when the GRN is done, before the qty reaches 100% of the order quntity For Example order qty 40, if the GRn has been done for 30 and you try to do a GRN for 14 the system will allow you to GRN But in the case that you have GRed 40 the PO is marked as delivery completed Regards Nelson
| | | ---------------Original Message--------------- From: kalyan Sent: Sunday, July 17, 2011 1:01 AM Subject: Overdelivery Tolerance in Purchase Order Hi Over Delivery tolerance is set for PO Qty only. So what happen, u r allowed to make GR for the PO Item Qty + 10% extra for that PO Item Qty Regards Kalyan | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |