RE:[sap-log-mm] Sub-components, for lack of a better term

Posted by lastarppguy (Production Manager)
on Jun 15 at 8:38 AM
Anindya,

We manage outside the system now, but you buy SAP, your expectation is to try and use it as much as possible to avoid running parallel systems and processes. Do you have any ideas how to use SAP for this issue?

---------------Original Message---------------
From: lastarppguy
Sent: Tuesday, June 14, 2011 4:26 PM
Subject: Sub-components, for lack of a better term

Looking for a way to manage this scenario in SAP. Any help is appreciated.
We receive a component from a vendor. We assign it a material #, stock it, and order and issue it to production orders as normal. Now, this particular component is actually made up of 5 pieces. Is there a way to setup this up in SAP so when the component is selected in a BOM or a Purchase Order in pulls in the list of pieces for reference purposes only? We do not want to inventory or costs those pieces individually.

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
Toolbox.com Marketplace: Take online training courses in SAP and other specialized areas of business and IT.
_.____.__

0 Response to "RE:[sap-log-mm] Sub-components, for lack of a better term"

Post a Comment