Hi all, I have the same problem and would like to post negative invoice with MIRO. Did you came up with a solution for this issue ? Thanks in advance.
| | | ---------------Original Message--------------- From: Satish Patankar Sent: Wednesday, September 28, 2011 12:08 PM Subject: How to Handle Negative Fees in MIRO? We need to treat sale and purchase separately, though both may be done with the same entity. You can link the customer master with vendor master by entering the customer number in vendor master (or the other way round). The two accounts can thus be managed jointly within AR/AP. Regards, Satish | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |
Posted by
Sap Land
05:56
If the planned delivery date changes on a fixed element (purchase order), you will see, Reschedule in, Reschedule out messages if the date does not meet your defined tolerances. Have you tried md06 for the entire plant, (collective tab). If you select the vendor tab you can restrict to just purchase orders, then on the material tab you can restrict to just purchased items, then restrict to just general messages, and reschedule messages. The list will generate. from the list you can do a find, and select specific messages (reschedule out, reschedule in,. review and cancel) This is a dynamic task list, and you can drill down into every message. Wondering why use a " printed report" when the planner can work directly from SAP.
| | | ---------------Original Message--------------- From: Celriz Sent: Friday, December 02, 2011 9:36 AM Subject: Transaction for viewing Expedite and De-expedite Report of Procure Material Hi Guys, I am looking for a T.code that can display the expedite and adaeexpedite dates of the externally procure material. Usually when you cut the PO you have delivery date created with the PO's. This way you know when your material is going to receive. What if this delivery date changes for any plannig reason or whatever.So there should be a way/ Report/T.code where you could view the original and revised delivery dates for the range of materials with their PO # respectively. Please if anyone has the answer to my request I will appreciate that | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Diane S SAP Logistics Material Management Helper
Posted helpful replies on 5 threads in a group to earn a Bronze Achievement Popular White Papers In the Spotlight _.____.__ |
Posted by
Sap Land
05:01
Go to t.code-ombt--->Click on groups(F6)---> Now click on Material Documents for goods Receipts WE WF Wo WW---> Maintain By Press Shift+F5 ------> Put no-----> Click EDIT on top (Tool Bar)----->click on insert year--->Put shown year then from no to no-----> Save ok and your problem will be solved.
| | | ---------------Original Message--------------- From: Rohan Dalal Sent: Friday, December 02, 2011 1:07 PM Subject: Number range for trans./event type WE in year 2011 does not exist Hello. I am getting error msg as period 2011/012 is not open for posting. the remedy suggested by system was to make changes in variant. I have also made those. Still it is showing error as posting period 2011/12 is not open for so n so type and G/L acc. Plz guide me in this respect. Thanks | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight SAP BusinessObjects: Dashboards and Analytics. Learn more about this Toobox.com Marketplace online course. _.____.__ |
Posted by
Sap Land
01:47
I can't offer you a solution, but I would be interested to know why you want to see stock level at the point of creating or releasing a PR. Surely you would also want to see demand for the material? Your system might show 100 or 1000 units in stock as you create the PR but that stock might be due to be consumed by the end of that day. I'm assuming that you are not running MRP. If you are then there should be no need to look at either stock level or demand as the system would be doing this for you and creating a req. accordingly. Hope this helps. ChrisO
| | | ---------------Original Message--------------- From: Abhijit Gharat Sent: Friday, December 02, 2011 5:19 AM Subject: How to Add Material Stock Column in PR Display ? Dear Team We want to have provision to check material stock during creation & release of PR. ( T code : ME51N, ME52N , ME53N & Release Tcode : ME54N ) Instead of checking each material stock through Line Selection -> Environment->Material stock., we want to check stock for all material code in one view, So can we add Material Stock Column for all above mentioned T-codes? Thanks in advance. Regards Abhijit | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | ChrisO SAP Logistics Material Management Enthusiast
Contributed 100 posts in a group to earn a Bronze Achievement Popular White Papers In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |
Posted by
Sap Land
00:51
Sir There is table EKPO for tax code, po no,mat code but vendor code is not available for po no and vendor code ekko Best Regards, Chandresh Kumar Gujar Sr.Officer(BIS-MM), GAIL(INDIA)LTD
| | | ---------------Original Message--------------- From: smslearn Sent: Monday, December 05, 2011 3:35 AM Subject: How to Know the Commodity of a PO ? Hi, I want to know the Commodity & Sub-Commodity of a PO which we place with the vendor. Is there any Tcode or table where we can give the Input of PO # and get the Commodity of it so that we can understand it easily? Thanks in advance. | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |
Posted by
Sap Land
00:34
Hi, I want to know the Commodity & Sub-Commodity of a PO which we place with the vendor. Is there any Tcode or table where we can give the Input of PO # and get the Commodity of it so that we can understand it easily? Thanks in advance. | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |
Posted by
Sap Land
00:34
You need to set up the number ranges for the inventory documents. It's in SPRO
| | | ---------------Original Message--------------- From: Rajat Mohanty Sent: Sunday, December 04, 2011 8:13 PM Subject: Physical Inventory Document Posting Hi all, I have created 2 materials to be stored in same locations with different stock. A physical inventory document to be created in MI01 postingblock. But I am getting an error message " Number range for trans.\ event type IB in year 2011 does not exist. Please guide Rajat | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | mack007 SAP Logistics Material Management Enthusiast